A52 Bottesford to Barrowby -
Roadworks
AMScott are the Managing Agent Contractor for the
Highways Agency in Area 7 covering the motorway and trunk
road network in the East Midlands.
We wish to inform you about forthcoming road works on the
A52 between Bottesford and Barrowby.
These essential works will include:
• Resurfacing and part reconstruction of the A52
carriageway
• Repairs to the concrete carriageway at Bottesford
• Traffic signing & lining improvements
• Streetlighting maintenance works
The works are currently programmed to start on Monday
21st July 2008 and are due to finish early-October 2008.
For the safety of motorists and road workers it will be
necessary to fully close the A52 overnight at various
times and over seven weekends. Overnight lane closures
with temporary traffic signals and convoy working will
also be required.
Overnight full road closures will be installed between
20:00hrs - 06:00hrs Saturday to Thursday and 22.00 –
06.00hrs Friday.
Full weekend closures will be installed between 22:00hrs
Friday to 06:00hrs Monday on 1st to 4th, 8th to 11th
August, 29th August to 1st September, 5th to 8th, 19th to
22nd and 26th to 29th September and 3rd to 6th October.
The A52 will be closed to through traffic between
Saxondale Island (A52/A46) and the Barrowby Junction
(A52/A1). Access to the A52 will be maintained for local
traffic from Saxondale Island. Access to Barrowby Village
will be maintained from the A1 and from the A52
(westbound from Grantham). There will be no access
through the works area between Muston and the Barrowby
Junction or between Tithby Road and Grantham Road at
Bingham. Refer to drawing no. E053105/LP/06 for further
details of full road closures.
The following diversions will be in place for A52 through
traffic, refer to drawing no. E053105/LP/05.
A1 Northbound
Traffic on the A1(T) Northbound wishing to exit onto the
A52(T) at Barrowby will be diverted along the A1(T) until
the A1/A17/A46 Junction at Newark where traffic will
proceed along the A46(T) Southbound until Saxondale
Island where the diversion ends.
A1 Southbound
Traffic on the A1(T) Southbound north of Newark wishing
to exit onto the A52(T) at Barrowby will be diverted onto
the A46(T) via the A1/A17/A46 Junction and will proceed
to Saxondale Island where the diversion ends. Traffic on
the A1(T) Southbound south of Newark will travel along
the A1(T) until the Harlaxton (A607) junction where they
will exit and re-join the A1(T) Northbound joining the A1
Northbound diversion route detailed on previous page.
A52/A46 Saxondale Island
Traffic at Saxondale Island (any approach) wishing to
continue on the A52(T) Eastbound towards Grantham will be
diverted via the A46(T) Northbound until the A1/A17/A46
Junction at Newark where they will be diverted onto the
A1(T) Southbound and exit at A52/A1 Junction at Barrowby.
Traffic wishing to travel from Grantham to Nottingham via
the A52(T) Westbound will be diverted onto the A1(T)
Northbound and join the A1 Northbound diversion detailed
on previous page.
Some noise disruption should be expected for residents
within the vicinity of the works, although we will do all
we can to keep this to a minimum.
We have consulted the local highway authorities, the
Environmental Health Officer and the emergency services
to help minimise the impact of these essential works.
The programme of the work may be subject to future
changes. We will keep you informed of any changes at
www.highways.gov.uk/a52sedgebrook where you can also
register your email address to receive regular updates.
Your co-operation and understanding would be greatly
appreciated. It is always our intention to reduce the
amount of disruption experienced by road users and
residents due to essential road maintenance.
If you have any queries regarding the works please
contact our 24 hour Network Control Centre on 01623
676555.
Yours faithfully
for AMScott
Roger Mansell
Project Manager